Trafalgar Road Corridor Study - Steeles Avenue to Highway 7

Trafalgar Road (Regional Road 3) Transportation Corridor Improvements – Steeles Avenue (Regional Road 8) to Highway 7, Town of Halton Hills

Status: Completed July 2016

Consultant: MMM Group Limited

Study Level: Schedule C

Purpose: To consider options for road improvements along the Trafalgar Road Corridor.

Scope: Halton Region will examine a wide range of road improvement alternatives in order to best address travel demand (to 2031) along Trafalgar Road as part of the study including intersection improvements, active transportation and over-all traffic operations. The impact of alternatives on social, cultural, economic and natural environments will also be evaluated and assessed during the study.

Key Recommendations: Pending study completion

Tentative Start of Construction: Capital Projects Maps & Indexes

Regional Contact: accesshalton@halton.ca

Please note that while the public, stakeholder and agency consultation applies to the entire Trafalgar Road Corridor, the Region anticipates filing the Environmental Study Report (ESR) to the Ministry of the Environment & Climate Change, for approval, in two parts:

Section 1

Steeles Avenue (Regional Road 8) to 10 Side Road (Regional Road 10), Town of Halton Hills

Section 2

10 Side Road (Regional Road 10) to Highway 7, Town of Halton Hills


Study Documents

Public Information Centre #1 - November 20, 2014

Public Information Centre #2 - June 17, 2015

Public Information Centre #3 - December 2, 2015

Environmental Study Report - June 2, 2016

Steeles Avenue to North of 10 Side Road FINAL ESR

North of 10 Side Road to Highway 7 FINAL ESR

Appendices from Steeles Avenue to Highway 7