Acton Water Supply Master Plan

Status:  Ongoing - Study initiated 2003

Consultant:   Dillon Consulting Limited

Study Level:  Schedule B

Purpose:  To identify the necessary improvements to the Acton Water Supply System to provide supply to the existing Urban Area.

Scope:  Halton Region will assess proposed improvements, including:

  • A revision to the Permit to Take Water (PTTW) for the Prospect Park well field.
  • Additional pre-treatment and filtration works at Prospect Park.
  • Addition to the existing water storage reservoir.

Key Recommendations:  Pending study completion.

Regional Contact:  Kelly Goorts, Project Manager Ext 3309  

Public Information Centre (PIC)