Halton Region is installing a large diameter watermain to connect to the Davis Road Pumping Station. The large diameter watermain will provide reliable access to high quality drinking water and service future development in north Oakville.

The large diameter watermain will run from Speers Road at Dorval Drive along Kerr Street, Shepherd Road, Cross Avenue and Argus Road to the Davis Road Pumping Station.


  • Blue square 1. Speers Road (Dorval Drive to Kerr Street) Final asphalt restoration - October 2018.
  • Turquoise square 2. Kerr Street (Speers Road to Shepherd Road Final asphalt restoration - October 2018.
  • Green square 3. Shepherd Road (Shepherd to Sixteen Mile Creek) Final asphalt restoration - October 2018.
  • Green-Yellow square 4. Microtunneling Sixteen Mile Creek Early March to late July. (Complete)
  • Yellow square 5. Jack and Bore Cross Avenue May 2018 to September 2018. (Complete)
  • Yellow-Orange square 6. Cross Avenue (Cornwall Road to Lyons Lane) Temporary asphalt restoration. October 2018.
  • Orange square 6A. Cross Avenue (Lyons Lane to Argus Road) Temporary asphalt restoration. October 2018.
  • Pink square 7. Argus Road (Cross Avenue to Trafalgar Road) Temporary asphalt restoration. October 2018.
  • Red square 8. Microtunneling Trafalgar Road November 2018 to December 2018.
  • Purple square 9. Davis Road November 2018 to April 2019.
  • Red line Work areas
Project Status:

In progress

Start Date:
End Date
:

February 2017
December 2018