Replacement of Culvert on Tremaine Road (Regional Road 22), 0.6 km South of Britannia Road (Regional Road 6) - PR-2280G

Building a Better Halton Logo
Location:

Tremaine Road (Regional Road 22), 0.6 km South of Britannia Road (Regional Road 6), Town of Milton

Description:

Beginning the week of December 4, 2017, Halton Region will be replacing a culvert on Tremaine Road (Regional Road 22), 0.6 km south of Britannia Road (Regional Road 6) in the Town of Milton. This work is required to maintain Halton Region’s infrastructure in a state of good repair.

The contractor for this project is NEI Construction Corporation, with project administration by AECOM Canada Ltd. Construction is expected to be completed by January 2018.

Utilities such as Union Gas, Hydro and Bell Canada have already started to locate and mark out their existing infrastructure to prepare for this construction. Please do not remove these marker stakes or paint markings. Staff will return to remove them once the project is complete.

A road closure will be required as part of this project from Friday, December 8, 2017 at 7 p.m. until Monday, December 11, 2017 at 6 a.m. In the event of poor weather or unforeseen conditions, the alternative date for the road closure will be from Friday, December 15, 2017 at 7 p.m. until Monday, December 18, 2017 at 6 a.m.


View larger map  External link
  • Blue lineDetour Route
Schedule:

December 2017 – January 2018
Road closure: Friday, December 8, 2017 at 7 p.m. to Monday, December 11, 2017 at 6 a.m.

Project No.

PR-2280G

Contact:

Rama Garigipati, Project Manager
905-825-6000 ext 7256
Rama.Garigipati@halton.ca

Additional Information: