Halton Region has initiated an Integrated Master Plan to complete the next region-wide Water, Wastewater and Multi-Modal Transportation Master Plans. The outcome of this work will be a long-term integrated servicing strategy for Regional infrastructure to accommodate future growth. The Integrated Master Plan will provide the strategies, policies and tools required to meet the future water, wastewater and transportation infrastructure needs.
Process
The study is being carried out in accordance with the requirements of Phases 1 and 2 of the Municipal Class Environmental Assessment (MCEA), (October 2000, amended 2007, 2011, 2015 and 2023), which is an approved process under Ontario’s Environmental Assessment Act.
The Integrated Master Plan will become the basis for, and will be used to support future Schedule C MCEA studies identified in the Master Plan. The Integrated Master Plan will be prepared with the level of investigation, consultation and documentation sufficient to fulfil the requirements for all Schedule B projects within the Master Plan. Anyone with an interest in this study is invited to participate virtually.
Public Engagement
Public and review agency consultation is a key element of the Integrated Master Plan process and input will be sought throughout this study, including Public Information Centres. The purpose of the first Public Information Center (PIC) is to explain the Master Plan process, identify problem and opportunities, and for public stakeholders to share their feedback.
Members of the public can visit the Water, Wastewater and Transportation Integrated Master Plan webpage on halton.ca to watch videos about the study and provide input through the online survey. The online PIC will be available from Monday, November 27 to Tuesday, January 2, 2024.
Comments
Please contact any of the project team members listed below or email imp@halton.ca if you have any questions or wish to be added to the Integrated Master Plan mailing list (water, wastewater and transportation). Comments are welcome throughout the duration of the project. Comments received through the course of this study will be considered and documented in the Integrated Master Plans.
Chris Fong, P. Eng.
Project Manager - Mobility Planning
Halton Region
1151 Bronte Road
Oakville, ON L6M 3L1
905-825-6000, ext. 7920
Mark Bajor
Project Manager - Water and Wastewater Planning
Halton Region
1151 Bronte Road
Oakville, ON L6M 3L1
905-825-6000, ext. 7921
Chris Hamel, P. Eng.
Consultant Project Manager
GM BluePlan Engineering Limited
Royal Centre
Suite 402 - 3300 Highway No. 7
Vaughan, ON L4K 4M3
416-703-0667
Cell: 416-577-2500
Information provided in response to this notice will be collected in accordance with the Municipal Freedom of Information and Protection of Privacy Act. With the exception of personal information, all comments will become part of the public record.